We knew we had the big club set, which would be situated at the end of the first block, twelve days into the shooting schedule. We had six-day episodes, so that was also quite tight, but fate would have it that our largest set would have to be shot on the second day of the schedule, which didn't leave much time to prepare, design, create and construct. Not only did the crew have to build a set and fully dress it, we also had to do a full LiDAR scan before it was shot so that we could have the CGI office space placed into that location/build for when Craig picks up his clothes the next morning. Unfortunately, and fortunately, I've been at this party before, so we put our heads down and made it happen. I think we were able to pull off something that we are all proud of. A. OVERHEAD VIEW OF THE SKY BAR. B. CRYING BLUE TREE PENCIL SKETCH BY CLARENCE MAJOR. C. SKY BAR ILLUSTRATION MAIN TABLE SETUP. A B C